Road Construction Notice - July 28-Aug. 3, 2025

Current Work

Meenan’s Cove Road - Phase 3 (between civic address 143 and Rockefeller Drive) – Fine grading, driveway shaping and base asphalt.

Ambassador Drive – Shouldering and landscaping.

Olympic Court – Shouldering and landscaping.

Captain Court – Shouldering and landscaping.

Aurora Boulevard – Curb backfilling and shaping, fine grading and base asphalt. This road is closed to thru traffic.

Elliott Road (at intersection with Palmer Brook Road) – Sewer installation. Traffic control will be in place. Expect delays and consider alternate routes where possible.

Detours

While it is anticipated the duration of construction on each street will be limited, motorists are advised to expect traffic delays during the construction period. The town will make every effort to always maintain one lane open or ensure flag persons and/or other forms of traffic control will be on site to direct traffic through the construction area.

Notes

The 2025 Street Capital Upgrades program is expected to operate into September. The work is being performed by Debly Enterprises Ltd. and subcontractors. A full list of streets identified for upgrades is available here.

The work performed, timelines and streets affected are all subject to change. The public will be notified of any major changes.

Residents can now subscribe to have Road Construction Notices delivered directly to their email inboxes. It takes only a couple of minutes to subscribe with a valid email address.

 

(Photo: Aurora Boulevard)

This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.