Road Construction Notice: August 17-23, 2026
Current Work
Cambridge Avenue - Traffic detour in place. Cambridge Ave is currently closed to through traffic between Quispamsis Road and Grasmere Avenue, Curb installation
Colt Drive - Shouldering, Driveway Reinstatement, Landscaping
Pacer Avenue - Shouldering, Driveway Reinstatement, Landscaping
Gondola Point Road Cross Cuts - Grading (Wednesday-Thursday), Paving (Friday)
Detours
While it is anticipated the duration of construction on each street will be limited, motorists are advised to expect traffic delays during the construction period. The town will make every effort to always maintain one lane open or ensure flag persons and/or other forms of traffic control will be on site to direct traffic through the construction area.
Notes
The 2026 Street Capital Upgrades program is expected to operate into late August or early September. The work is being performed by Galbraith Construction Ltd. and subcontractors. A full list of streets identified for upgrades is available here.
The work performed, timelines and streets affected are all subject to change. The public will be notified of any major changes.